Project progress

Description

According to the updated plan

Actual progress Planned progress
# Water transmission project Relative value Aug. 21, 2018 Aug. 21, 2018
1 Overall project progress 100/00% 85.92% 100%
1.1 Procurement 60.00% 95.1% 100%
1.2 Construction 40.00% 72.17% 100%