Description |
According to the updated plan |
|||
Actual progress | Planned progress | |||
# | Water transmission project | Relative value | Aug. 21, 2018 | Aug. 21, 2018 |
1 | Overall project progress | 100/00% | 85.92% | 100% |
1.1 | Procurement | 60.00% | 95.1% | 100% |
1.2 | Construction | 40.00% | 72.17% | 100% |